Design/build team rapidly mobilizes, creates nimble schedule to remediate site cost effectively and on time

Manufacturing Client Milwaukee, WI

Project Highlights

Client Challenge
After decades of industrial use, a contaminated site owned by our manufacturing client was deemed a brownfield. Previously used as a wastewater treatment and hazardous material storage area, the resulting contamination posed a threat to groundwater. When approached to remediate the site, we were also faced with the challenge of an extremely compressed construction schedule that required us to meet key regulatory milestones and a fast-approaching winter. With only five days of float in the schedule, any delays would push the project into the spring adding significant time and remobilization costs. The site's location in an urban environment also posed inherent security risks. Our reputation for overcoming challenges and maintaining tight schedules was critical for keeping this repeat client.

Our Approach
Our design/build team used a detail-oriented approach in planning the project to meet the client's objectives. Understanding that a high level of teamwork, efficiency, and schedule management was crucial to achieving critical path milestones, we committed our design and construction resources to design and construct a cap and containment solution that included a slurry wall, perimeter toe drain, and asphalt cap. Unexpected lead contamination in the soil was encountered during construction which required the stabilization of the additional impacted soil.

Through a design/build approach, we refined the budget and reduced labor costs by maximizing equipment operator utilization and sequencing and consolidating tasks accordingly. We approached problems as a unified team setting the expectation that each functional group would meet the schedule and budget for our client. Project was completed under budget and prior to temperatures dropping to the point where the local asphalt plants shut down.

Value Delivered

  • Integrated multiple design/build services to facilitate a shortened schedule
  • Worked as one team to ensure that the design, permitting and construction functioned seamlessly
  • Cost-effectively delivered a challenging design/build project on time
  • Client consistently noticed our adherence to safety requirements throughout the project and provided a written letter to compliment our efforts at the end of the project
  • Successfully mitigated unforeseen site conditions with minimal impact to the project budget
  • Saved a net $45,000 on permitting costs by using an available code variance
  • Worked around the clock in an urban environment to meet schedules and ensure the security of contractors

For more information on this project, contact Walter Kurzeja